Every factory has a minimum order quantity, and every buyer wants it lower. The useful conversation is not about the number itself but about what it is made of — because once you can see the components, you can often design around them.
Why the minimum is per colour, not per order
A knitwear style is not printed or cut from fabric; it is knitted from yarn. Yarn is bought in dye lots, and a dye lot has its own minimum at the spinner. Knit 100 pieces in one colour and the factory still has to buy a full lot of that yarn, set the machine for that colour sequence, and knit a first-off piece before production can start.
That is why an order of 900 pieces in three colours is a different proposition from 900 pieces in one colour: three colours means three yarn lots, three set-ups and three first-off approvals.
What actually scales with volume — and what does not
- Yarn minimum: per colour, fixed. This is the biggest driver of the MOQ.
- Machine set-up and first-off: per style per colour, fixed.
- Sampling: per style, fixed — and paid separately from bulk.
- Knitting and finishing minutes: proportional to pieces, so these fall per unit as volume rises.
In practice, the fixed costs are what make a 100-piece order expensive per unit rather than impossible. When a buyer asks to start smaller, the honest answer is often: fewer colours, not fewer pieces.
Four ways a first order gets smaller
1. Reduce the colour count
One colour at 300 pieces is a legitimate first order. Five colours at 60 pieces each is not, because the factory would still buy five yarn lots.
2. Use a stock yarn
Standard colours in a stock yarn skip the dyeing lead time and its minimum. The trade-off is a palette you did not define yourself.
3. Combine styles on one yarn
Two styles in the same yarn and colour can share a yarn lot, which sometimes lets a buyer split the minimum across two styles rather than doubling it.
4. Plan a re-order before you launch
A first order that is expected to be followed by a re-order is easier to schedule than a one-off. Tell the factory your season plan; it changes how they quote.
Colour is usually more expensive than quantity. One colour at 300 pieces beats three colours at 100 each — every time.
A realistic first order
A small brand's first knitwear order is commonly two to three styles, one or two colours each, at 300 pieces per style per colour. That is enough to test a shape in the market and enough to keep the unit cost sane. Sampling runs first — 7–10 days for a first sample — and bulk follows at 45–55 days after approval.
If your plan needs something smaller than that, say so at the inquiry stage. Sometimes the answer is a different yarn, sometimes it is a different construction, and sometimes it is honestly "not on this floor" — which is more useful to hear before you have paid for samples.